Unusual Lifting & Pulling Projects:

  Water Catchments Stabilisation / Gibraltar.

The Water Catchments on the Rock of Gibraltar required decommissioning  and stabilizing.

Almost 10,000 soil-nails needed installing requiring the use of a number of heavy duty impact drills and the removal of 1000,s of corrugated tin sheets originally used to catch rain water for the island. 

ALPS supplied the specialised Lifting & Pulling equipment required to manoeuvre the 15-Ton+ rock drills and purpose built carriages up and down the ancient 45% sloping sand-dune.

ROCK DRILL & CARRIAGE AT ALMOST 20-TONS

 

The Millennium Dome Construction Project

The Millennium Dome construction project required the design and installation of a unique multi-winch lifting system in order that the central hub and subsequent circumferential "Nets" could be raised to their installed height. 
ALPS were commissioned to design and procure the system that would perform this difficult task. 
36 Double reeved 6 Ton linear wire rope Jacks (SP6) were installed at the mast head and powered from a purpose designed hydraulic power pack also situated at the top of each mast. 
A combined pulling force of 432 Tons raised each section of the roof "Net" and enabled the Industrial Roped Access workers, also supplied by ALPS, to make the socket attachments at the node. 
Access to each of the mast head platforms was made easy by the design and installation of 12 powered Man riding cradles each carrying three men with their materials to the mass head platform 90 mts. off the ground, in 10 minutes.

MILLENNIUM DOME ROOF SUPPORT NET INSTALATION

The Combined Capacity Of The 36 X Wire Rope "Net Lifting" Winches Was 432 Tons

The "Net" installation Winching System and Suspended Access Man riding solutions were designed and procured by ALPS. 
On site induction and continuous training in the safe use of the equipment was also carried out by ALPS. 

6 X 24M RADIAL ACCESS PLATFORMS
6 x 24M Radial access platforms were supplied


RADIAL ACCESS PLATFORM SUPPORTED AT 24Mts

12 X 2M MAST ACCESS CRADLE  6-TON HYDRAULIC WINCHES - 3 PER MAST

12 X mast access platforms were installed:                        3 X 6T hydraulic winches per mast:

Radial Cable Access Platforms:

24mtr. Modular Access Platform shown in situ. 
Useful working width 680 mm. 
Constructed from 8 x 3M alloy floors and sides. 
Steel end hangers support the 3M end sections and suspend the Access Platforms with steel chains from the radial cables. 
Each platform was tested for a capacity of five men with three men permitted in the centre. 
A UDL of 450Kgs was permitted. 
6 No. platforms were used by the American specialist roofing contractors BIRDAIR and DCCI for installation of cable clamps and roof fabric. 
As all major components were standard the 144mtrs of platform sections could be delivered to site and erected within the short time frame available.

  


 
BACK TO > Options Page
BACK
FORWARD TO  > Roped Access
NEXT